Warehouse terminal with capacity of 112 000 tons at oil-extracting factory with a capacity of 5000 tons per day

Main » Our projects » Warehouse terminal with capacity of 112 000 tons at oil-extracting factory with a capacity of 5000 tons per day, as part of production and logistics complex
GC Sodrugestvo, LLC / 2012

Client:  GC Sodrugestvo, LLC

Works provided: supply of 16 silos, transport equipment, racks. Installation of equipment.

Specifications: silos with a capacity of 10,010 m³. Loading silos with a capacity of 600 t / h, with unloading capacity of 300 t / h.Total storage capacity: 160 m³. Metal silos with flat bottom d = 24 m

Project implementation period: July 2011 – November 2012